Blog · Roads and access

Rawalpindi Ring Road and DHA Gandhara: what the delay means

Not open yet (23 November 2026). The 38.3 km Rawalpindi Ring Road is built from Banth to Thalian, but on 14 November its inauguration was postponed for the ninth time with no new date, and the Thalian Interchange where it meets the motorway near DHA Gandhara is still unfinished.

Updated 26 November 2026 · Land14

Update 26 November 2026: the Ring Road was not inaugurated during the Punjab Chief Minister’s visit on 24 November, and reports now expect it to open around mid-December 2026, with no official date confirmed (PakWheels, 24 Nov 2026). Every announced date and cost revision since 2025 is in our Rawalpindi Ring Road tracker.

The Rawalpindi Ring Road is the single biggest road project near DHA Gandhara (DHA Phase 9 Islamabad), and it is the reason our DHA Gandhara location guide lists the Ring Road at about five minutes from the site. But "the Ring Road is coming" has been said for years. This page sets out what is actually built, what is not, and what has been reported in the last few weeks, with a source for every fact, so you can judge the access story yourself instead of trusting a sales pitch.

The Ring Road in one table (status on 23 November 2026)

ItemStatusSource
Route38.3 km, from Banth on GT Road (Rawat) to the Thalian motorway interchangeExpress Tribune, 5 Nov 2026
Main carriagewayReported complete from Banth to ThalianExpress Tribune, 5 Nov 2026
Banth, Chak Beli Khan, Adiala and Chakri interchangesReported completeExpress Tribune, 5 Nov 2026
Thalian Interchange (motorway link)Not completeExpress Tribune, 5 Nov 2026
Toll booths and weigh stationsStill being installedExpress Tribune, 5 Nov 2026
InaugurationPostponed for the 9th time on 14 Nov 2026; no new date; ceremony to be announced on 24 hours' noticeExpress Tribune and ProPakistani, 14 Nov 2026
Opening to trafficPlanned before the formal ceremony; on 4 Nov an official said remaining work could take a month or longerProPakistani, 4 Nov 2026; Express Tribune, 14 Nov 2026
Project costPKR 50.4 billion (third revised PC-I, includes Thalian)Express Tribune, 17 Oct 2026

Sources: Express Tribune, "Ring Road opening delayed yet again", Express Tribune, "Ring Road cost jumps to Rs50.4b", Express Tribune, 14 Nov 2026, ProPakistani, 14 Nov 2026 and ProPakistani, 4 Nov 2026.

Is the Rawalpindi Ring Road open?

No. On 14 November 2026 the Rawalpindi Ring Road Authority postponed the inauguration for the ninth time and decided not to announce another date. The ceremony will now be called on just 24 hours' notice, and officials plan to open the road to general traffic before it, according to the Express Tribune and ProPakistani. One interchange is still unfinished, and the toll plazas, computerised toll collection and weigh stations are still being completed. This followed the eighth postponement, of the 6 November ceremony, reported by the Express Tribune on 5 November; on 4 November a district official told ProPakistani the remaining work could take a month or longer, so December is the earliest realistic window. Earlier in 2026, Zameen News reported that the road was expected to open first and operate without the Thalian Interchange, which would follow later. That still looks like the most likely order of events, but nobody has fixed a date, so treat any "opening next week" claim with care.

Why the Thalian Interchange matters most for DHA Gandhara

For a DHA Gandhara buyer, the important part is not the whole 38 km but the southern end. The Ring Road finishes at Thalian, where it is being joined to the motorway, and DHA Gandhara is reported to sit on the M-2 near Chakri Road and the Thalian Interchange. In plain terms: until Thalian is finished, the Ring Road does not yet give the motorway corridor the direct link it was designed for.

  • It was redesigned to carry more traffic. In May 2025 the Express Tribune reported that Thalian was being redesigned as a "broad-based" interchange to handle higher traffic volumes.
  • The traffic forecast is large. Dawn reported in January 2026 that more than 18,000 vehicles were expected to move from the Ring Road onto the motorway, which is why officials said a full interchange was needed to avoid congestion.
  • The money is now approved. The third revised PC-I of PKR 50.4 billion, approved by Punjab's PDWP on 12 October 2026, includes the cost of building Thalian. Land acquisition for the interchange is reported complete.

The Chakri interchange of the Ring Road, which is reported complete, is also relevant because Chakri Road is the main local road into the area. See the full route picture and drive times in our guide to where DHA Gandhara is and how to reach it.

How the cost and timeline have moved

The Ring Road has been repeatedly re-planned. These are the reported figures, so you can see why "almost finished" has lasted so long:

VersionReported cost
Original PC-IPKR 26.9 billion
First revisionPKR 32.9 billion
Second revisionPKR 46.4 billion
Third revision (approved 12 Oct 2026, includes Thalian)PKR 50.4 billion

Source: Express Tribune, 17 October 2026. The road also includes a large number of structures; the Express Tribune listed 2 river bridges, 7 nullah bridges, 1 railway bridge, 11 overpasses, 10 subways and 53 culverts in 2025.

What it means if you are buying in DHA Gandhara

Roads change how easy a place is to live in, and that is one of the factors in our list of what moves DHA Gandhara plot prices. But be careful with anyone who tells you a price will jump on a particular day because of the Ring Road. Nobody can promise that. What you can do is plan around the facts:

  1. If you are investing for the long term, the Ring Road and the Thalian link are confirmed, funded projects. The open questions are timing, not whether they will happen.
  2. If you plan to build and live soon, remember that DHA Gandhara itself has not been launched yet. The official launch, the DHA Gandhara payment plan and the ballot are all still awaited, so the road is likely to open well before you could build a house.
  3. If someone uses the Ring Road to rush you, slow down. "Prices will double when the Ring Road opens, pay today" is pressure, not information. Follow the steps in how to check a DHA file is genuine before any money moves.

What to watch next

  • A confirmed inauguration date for the main road, probably without Thalian at first.
  • Construction progress at Thalian, the part that matters most for the M-2 side.
  • Toll rates, which have not been officially published.
  • DHA's own announcement on the DHA Gandhara launch, which will matter more to buyers than any road news.

We add every confirmed step to our DHA Gandhara launch news page on the day it happens. If you want a WhatsApp message when either the Ring Road opens or DHA announces the launch, join our launch alert list. And if you are weighing the corridor more broadly, our comparison of DHA Gandhara and Capital Smart City looks at how the two neighbours on the M-2 differ.

Want to see where the Ring Road meets DHA Gandhara?

WhatsApp +92 333 5700339

Questions

Is the Rawalpindi Ring Road open?

Not as of 23 November 2026. On 14 November the inauguration was postponed for the ninth time and no new date was announced. Officials say the road will open to general traffic before the formal ceremony, which will be announced at 24 hours' notice (Express Tribune, ProPakistani).

Is the Thalian Interchange complete?

No. The Express Tribune reported on 5 November 2026 that four interchanges (Banth, Chak Beli Khan, Adiala and Chakri) were complete but Thalian was not, because of its broad-based design. Its cost is included in the PKR 50.4 billion revised PC-I.

How far is DHA Gandhara from the Rawalpindi Ring Road?

About 5 minutes by road, as reported. DHA Gandhara is on the M-2 near Chakri Road and the Thalian Interchange, where the Ring Road meets the motorway.

Will the Ring Road increase DHA Gandhara prices?

Better road access is one of the factors that supports prices, but no one can promise a specific rise on a specific date. Today, 1 Kanal DHA Gandhara files start from PKR 7.5 million in the market.