Rawalpindi Ring Road tracker: every date, cost and delay
Not open yet. As of 26 November 2026 the inauguration has been postponed nine times, no date is confirmed, and opening is now expected around mid-December 2026. Below: every announced date, every cost revision and what is still unfinished, with sources.
Updated 26 November 2026 · Land14
This page is a dated record of the Rawalpindi Ring Road: every opening date that was announced and missed, every cost revision, and what is still unfinished. Each line links to the news report it comes from. We update it whenever a new report appears. If you write about the Ring Road, you are welcome to use it as a source (see How to cite this tracker).
Status today (26 November 2026)
| Item | Status | Source |
|---|---|---|
| Route | 38.3 km, six lanes, from Banth on GT Road to the Thalian interchange on the M-2 motorway | ProPakistani, 28 Oct 2026 |
| Main carriageway | Reported complete | PakWheels, 24 Nov 2026 |
| Banth, Chak Beli Khan, Adiala Road and Chakri interchanges | Reported complete | PakWheels, 24 Nov 2026 |
| Thalian interchange | Not complete | PakWheels, 24 Nov 2026 |
| Toll plazas, electronic toll collection, weigh stations | Not complete | Express Tribune, 14 Nov 2026; PakWheels, 24 Nov 2026 |
| Inauguration | Postponed nine times; no date announced. Ceremony to be called at 24 hours’ notice | Express Tribune, 14 Nov 2026 |
| Opening to traffic | Officials say traffic will be allowed before the formal ceremony; now expected around mid-December 2026 if the remaining work is finished | Express Tribune, 14 Nov 2026; PakWheels, 24 Nov 2026 |
| Latest cost reported | Rs50.4 billion (third revised PC-I); Express Tribune reported Rs51.32 billion, passing Rs52 billion, on 14 Nov | Dawn, 20 Oct 2026; Express Tribune, 14 Nov 2026 |
Short answer: as of 26 November 2026 the Rawalpindi Ring Road is not open. It was not inaugurated during Punjab Chief Minister Maryam Nawaz’s visit on 24 November, and no official inauguration date has been confirmed (PakWheels, 24 Nov 2026).
Every opening target, in order
These are the dates officials gave for completion, opening or inauguration, in the order they were reported. Outlets number the postponements differently, so we list the dates rather than rely on one count.
| Reported | What was announced or happened | Source |
|---|---|---|
| 17 Nov 2025 | PC-I revised and cost raised from Rs33 billion; RDA says the project is on track for March 2026 | ProPakistani, 17 Nov 2025 |
| 26 Dec 2025 | 2025 deadline missed; completion now projected for March 2026; cost escalated from Rs33b to Rs50b | Express Tribune, 26 Dec 2025 |
| 12 May 2026 | New target set for mid-June after earlier dates were missed | ProPakistani, 12 May 2026 |
| 18 May 2026 | Around 85% complete; main route to open by mid-June, without the Thalian interchange and motorway link (phase two) | ProPakistani, 18 May 2026 |
| 9 Jun 2026 | Officials say over 90% complete and the road will open to traffic on 15 June | Express Tribune, 9 Jun 2026 |
| 26 Jun 2026 | Revised PC-I of Rs46.64 billion approved; road “awaiting inauguration” | Express Tribune, 26 Jun 2026 |
| 3 Jul 2026 | 29 June inauguration missed; now expected in the second week of July | Express Tribune, 3 Jul 2026 |
| 13 Jul 2026 | 14 August set as the next target; earlier targets of 30 Dec 2025, 30 Mar, 30 May, 15 Jun and 22 Jun listed as missed | ProPakistani, 13 Jul 2026 |
| Aug 2026 | 14 August passed without inauguration; toll booths and system still under construction; cost reported at Rs47 billion | Express Tribune, Aug 2026 |
| 10 Sep 2026 | Route complete except toll booths; authorities awaiting a date from the Chief Minister | Express Tribune, 10 Sep 2026 |
| 28 Oct 2026 | Commissioner aims to open the road fully in November; Thalian interchange, toll booths and electronic tolling still pending | Express Tribune, 28 Oct 2026; ProPakistani, 28 Oct 2026 |
| 4 Nov 2026 | Opening to traffic delayed by about another month for toll plazas and weigh stations | ProPakistani, 4 Nov 2026; Dawn, 4 Nov 2026 |
| 5 Nov 2026 | Ceremony planned for 6 November deferred (eighth postponement); new date after toll system and weigh stations are finished | Express Tribune, 5 Nov 2026 |
| 14 Nov 2026 | Ninth postponement; no new date; ceremony at 24 hours’ notice; road to open to traffic before the ceremony | Express Tribune, 14 Nov 2026 |
| 24 Nov 2026 | Not inaugurated during the Chief Minister’s visit; opening now expected in mid-December 2026, not confirmed | PakWheels, 24 Nov 2026 |
How the cost has changed
| When | Reported cost | Source |
|---|---|---|
| 2021 | Rs23.6 billion | PakWheels, 24 Nov 2026 |
| 2022 | Rs26.969 billion | PakWheels, 24 Nov 2026 |
| 2024 | Rs32.9 billion | PakWheels, 24 Nov 2026 |
| January 2026 | Rs47 billion | PakWheels, 24 Nov 2026 |
| June 2026 | Rs46.64 billion (revised PC-I approved) | Express Tribune, 26 Jun 2026 |
| October 2026 | Rs50.4 billion (third revised PC-I) | Dawn, 20 Oct 2026; PakWheels, 24 Nov 2026 |
| 14 Nov 2026 | Rs51.32 billion, then over Rs52 billion | Express Tribune, 14 Nov 2026 |
Figures differ between outlets and between the approved PC-I and running estimates, so treat any single number as “as reported on that date”. PakWheels reports that the RDA has paid Rs35 billion to the contractor so far (PakWheels, 24 Nov 2026).
What is still holding it up
- Tolling: toll plazas and the electronic toll collection system. The authority does not want the road open until vehicles cannot pass without paying (Express Tribune, 5 Nov 2026).
- Weigh stations for heavy vehicles (ProPakistani, 4 Nov 2026).
- Thalian interchange at the motorway end, treated as a separate phase (ProPakistani, 18 May 2026; PakWheels, 24 Nov 2026).
Background
The project has been pending for many years (Express Tribune puts it at 24 years). Express Tribune reports that former Prime Minister Imran Khan laid its foundation stone in March 2022 (Express Tribune, 14 Nov 2026); ProPakistani reports that Prime Minister Shehbaz Sharif laid a foundation stone at Rawat on 8 August 2023 (ProPakistani, 4 Nov 2026). The Rawalpindi Development Authority (RDA) is executing the project and the Punjab Ring Road Authority will run it once complete.
Why we track it
DHA9 is an independent guide to DHA Gandhara (DHA Phase 9), which is planned near the Thalian end of the Ring Road. For how the road affects plot buyers, read Rawalpindi Ring Road and DHA Gandhara. Note that DHA Islamabad-Rawalpindi said on 16 September 2026 that Gandhara has not been launched; always verify any file with DHA before paying (how to verify a DHA file).
How to cite this tracker
You may quote or reproduce any table on this page with a link to it: “Rawalpindi Ring Road tracker, DHA9 (dha9.com/rawalpindi-ring-road-tracker/), updated 26 November 2026.” Spotted a newer report or an error? Send it on WhatsApp +92 333 5700339 or to info@dha9.com and we will update the page.
Buying near the Thalian end of the Ring Road?
WhatsApp +92 333 5700339Questions
Is the Rawalpindi Ring Road open?
Not as of 26 November 2026. It was not inaugurated during the Chief Minister’s visit on 24 November and no official date has been confirmed. Reports now expect it to open around mid-December 2026 if the toll plazas and weigh stations are finished (PakWheels, 24 Nov 2026; Express Tribune, 14 Nov 2026).
How many times has the Ring Road opening been postponed?
Express Tribune called the 14 November 2026 delay the ninth postponement of the inauguration. Outlets count differently, so this page lists every announced date in order instead.
How much does the Rawalpindi Ring Road cost?
The third revised PC-I puts it at Rs50.4 billion (Dawn, 20 Oct 2026). Express Tribune reported on 14 November 2026 that the estimate had reached Rs51.32 billion and passed Rs52 billion.
What is still unfinished on the Ring Road?
The toll plazas and electronic toll collection, the weigh stations, and the Thalian interchange at the motorway end.